本網濟寧訊 8月29日,新驛(yi)煤礦歷時8小(xiao)時施工,圓滿(man)完成副(fu)井平衡尾繩更換任務,為礦井安全(quan)高效(xiao)運行打下堅實(shi)基礎。
為確保(bao)本次換繩(sheng)(sheng)工(gong)程(cheng)順利進行(xing)(xing),該礦施(shi)(shi)(shi)工(gong)前組(zu)(zu)織召(zhao)開工(gong)程(cheng)研討(tao)會(hui),從安(an)(an)全(quan)(quan)保(bao)障、施(shi)(shi)(shi)工(gong)步驟、人員組(zu)(zu)織等方(fang)面(mian)進行(xing)(xing)深入研討(tao),編制安(an)(an)全(quan)(quan)嚴(yan)密的(de)施(shi)(shi)(shi)工(gong)技術(shu)措施(shi)(shi)(shi),抽調28名(ming)技術(shu)骨干成(cheng)立4個(ge)施(shi)(shi)(shi)工(gong)小組(zu)(zu),科學分配(pei)工(gong)作(zuo)任(ren)務、全(quan)(quan)面(mian)做好(hao)換繩(sheng)(sheng)準備工(gong)作(zuo)。在施(shi)(shi)(shi)工(gong)過(guo)(guo)程(cheng)中,該礦管(guan)理(li)人員全(quan)(quan)程(cheng)盯靠(kao)指揮,嚴(yan)格按照措施(shi)(shi)(shi)要求作(zuo)業,使用舊繩(sheng)(sheng)帶新(xin)繩(sheng)(sheng)的(de)施(shi)(shi)(shi)工(gong)工(gong)藝,采用平行(xing)(xing)交替作(zuo)業方(fang)法更(geng)換新(xin)繩(sheng)(sheng)。經(jing)過(guo)(guo)全(quan)(quan)體施(shi)(shi)(shi)工(gong)人員的(de)團結協作(zuo)和不懈努力,換繩(sheng)(sheng)工(gong)作(zuo)圓(yuan)滿完成(cheng),再次刷新(xin)紀錄(lu)。(姜博)